Stoneridge Site Progress

Stoneridge Semi-D 6A: Internal paint in progress as of 1/10/2019

Stoneridge Semi-D 6A: Tiling In progress as of 1/10/2019

Stoneridge Cluster 6A1: Roof covering completed as of 1/10/2019

Stoneridge Cluster 6A1: Staircase in progress as of 1/10/2019

Stoneridge Semi-D 6B: Internal paint in progress as of 1/10/2019

Stoneridge Semi-D 6B: Ceiling in progress as of 1/10/2019

Stoneridge Cluster 6B1: Painting undercoat in progress as of 1/10/2019

Stoneridge Cluster 6B1: Upper roofbeam in progress as of 1/10/2019

Stoneridge Bungalow 6C: External paint in progress in progress as of 1/10/2019

Stoneridge Bungalow 6C: Ceiling in progress as of 1/10/2019

Stoneridge Bungalow 6D: Fencing structure in progress as of 1/10/2019

Stoneridge Bungalow 6D: Tiling works in progress as of 1/10/2019

Stoneridge Bungalow 6E: Window Panel installation in progress as of 1/10/2019

Stoneridge Bungalow 6E: Plaster works in progress as of 1/10/2019